Plan: Epic Implementation Roadmap
Purpose
Transform the feature list from /rai-epic-design into a sequenced implementation plan with intermediate milestones, parallel work streams, and progress tracking mechanisms. Create a roadmap that maximizes learning, minimizes risk, and enables visible progress.
Core principle: Risk early, reward early. Tackle uncertain features first while momentum is high; deliver quick wins to validate approach and build confidence.
Planning philosophy: Plans are hypotheses, not commitments. The value is in thinking through sequencing, not in perfect predictions. Adjust as you learn.
Mastery Levels (ShuHaRi)
Shu (守): Follow all steps completely; create sequenced feature plan with explicit milestones; define at least one walking skeleton milestone and one MVP milestone.
Ha (破): Adjust milestone granularity based on epic size; combine or skip steps for small epics (<5 features); customize risk assessment based on domain knowledge.
Ri (離): Create domain-specific sequencing patterns; develop team velocity models; integrate with organizational planning rhythms (PI Planning, quarterly goals).
Context
When to use:
- •After
/rai-epic-designhas produced a scope document with features - •Before starting first feature implementation
- •When features have complex dependencies requiring coordination
- •When stakeholders need visibility into progress checkpoints
- •When multiple work streams could run in parallel
When to skip:
- •Very small epics (2-3 features) with obvious linear sequence
- •Emergency fixes with single critical path
- •Epics already in progress (use for new epics only)
Inputs required:
- •Epic scope document:
work/epics/e{N}-{name}/scope.md - •Feature list with sizes and dependencies
- •Calibration data (
.raise/rai/memory/calibration.jsonlif available) - •External constraints (deadlines, dependencies, resource availability)
Outputs:
- •Updated epic scope document with sequenced plan
- •Feature execution order with rationale
- •Intermediate milestones (walking skeleton, MVP, complete)
- •Progress tracking setup
- •Parallel work identification
Steps
Step 0: Emit Epic Start (Telemetry)
Record the start of the plan phase:
rai memory emit-work epic {epic_id} --event start --phase plan
Example: rai memory emit-work epic E9 -e start -p plan
Step 0.5: Query Context
Load relevant sequencing patterns and calibration from unified context:
rai memory query "sequencing calibration planning" --types pattern,calibration --limit 5
Review returned patterns before proceeding. Calibration data informs realistic estimates.
Verification: Context loaded; relevant patterns noted.
If context unavailable: Run
rai memory buildfirst, or proceed without patterns.
Step 1: Review Epic Design Output
Load and understand the epic scope before planning.
Review:
- •Epic objective and value proposition
- •Feature list with sizes (T-shirt or SP)
- •Dependencies identified in
/rai-epic-design - •Done criteria (feature and epic level)
- •Risks identified
Capture:
- •Total features and estimated effort
- •Key constraints (deadline, external dependencies)
- •Architectural decisions that affect sequencing
Verification: Can explain the epic scope in 60 seconds.
If you can't continue: Epic design incomplete → Run
/rai-epic-designfirst.
Step 2: Identify Critical Path
Determine which features are essential for others to proceed.
Critical path analysis:
- •List features that block other features (dependencies)
- •Identify features with external dependencies (APIs, infrastructure)
- •Find features with highest uncertainty or risk
- •Map the longest chain of dependent features
Dependency types:
- •Hard: Cannot start B until A complete (technical requirement)
- •Soft: B could start early but benefits from A (learning, patterns)
- •External: Depends on factors outside the epic (APIs, approvals)
Critical path diagram:
F{N}.1 (foundation) ← CRITICAL PATH START
↓
F{N}.2 (core capability)
↓
F{N}.3 ──┐
│ (parallel possible)
F{N}.4 ◄─┘
↓
F{N}.5 (integration) ← CRITICAL PATH END
Verification: Critical path identified with duration estimate.
If you can't continue: Dependencies unclear → Return to
/rai-epic-designStep 6 (Map Dependencies).
Step 3: Apply Sequencing Strategy
Order features using proven sequencing strategies.
Primary strategy: Risk-First (Lean principle)
Tackle the most uncertain features early when:
- •Energy and focus are highest
- •More time remains for pivots
- •Learning can inform later features
Risk indicators:
- •New technology or unfamiliar patterns
- •Integration with external systems
- •Unclear requirements (even after design)
- •Performance or scalability unknowns
Secondary strategy: Walking Skeleton
Build minimal end-to-end functionality first:
- •Proves architecture works
- •Enables early integration testing
- •Provides demo-able progress quickly
- •Validates assumptions before heavy investment
Tertiary strategy: Quick Wins
Include early features that:
- •Build momentum and confidence
- •Provide immediate value
- •Enable parallel work streams
- •Validate tooling and processes
Sequencing decision matrix:
| Feature Type | Sequence Position | Rationale |
|---|---|---|
| High risk, blocking | Early | Reduce uncertainty, unblock others |
| Walking skeleton | Early | Prove architecture, enable integration |
| Quick win, non-blocking | Early-middle | Build momentum, validate process |
| Core functionality | Middle | Build on foundation |
| Polish, optimization | Late | Refinement after core complete |
| External dependency | Based on availability | Coordinate with external timeline |
Verification: Each feature has sequencing rationale documented.
If you can't continue: Multiple valid orderings → Choose risk-first as default; document alternatives.
Deep dive: See
_references/sequencing-strategies.mdfor detailed philosophy and anti-patterns.
Step 4: Identify Parallel Work Streams
Find opportunities for concurrent work.
Parallel opportunities:
- •Features with no mutual dependencies
- •Features in different parts of the codebase
- •Features that can share early patterns/infrastructure
- •Research/documentation that doesn't block code
Parallel constraints:
- •Resource availability (single person = limited parallelism)
- •Integration risk (too much parallel work = merge conflicts)
- •Context switching cost (AI-assisted work has low switching cost)
Parallel work diagram:
Time →
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Stream 1: F{N}.1 ─────► F{N}.2 ─────► F{N}.5
↓ enables
Stream 2: F{N}.3 ─────► merge
↑
Stream 3: F{N}.4 ───────┘
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Verification: Parallel opportunities documented with merge points.
If you can't continue: No parallel opportunities → Sequential is valid; document why.
Step 5: Define Milestones
Create intermediate checkpoints for progress visibility.
Standard milestone pattern:
| Milestone | Definition | Purpose |
|---|---|---|
| M1: Walking Skeleton | Minimal E2E path through system | Prove architecture, enable integration |
| M2: Core MVP | Essential features complete | Demonstrate value, gather feedback |
| M3: Feature Complete | All planned features done | Ready for polish/release |
| M4: Epic Complete | Done criteria met, retro done | Ready for /rai-epic-close |
For each milestone, define:
- •Name: Clear, meaningful label
- •Features included: Which features must be complete
- •Success criteria: How to verify milestone reached
- •Demo capability: What can be shown/tested
- •Feedback opportunity: What questions can be answered
Milestone heuristics:
- •Walking Skeleton: 1-3 features (smallest demonstrable value)
- •Core MVP: 50-70% of features (enough for meaningful feedback)
- •Feature Complete: 100% planned features (polish can follow)
Milestone template:
### Milestone M{N}: {Name}
**Features included:**
- F{X}.{Y}: {Feature name}
- F{X}.{Z}: {Feature name}
**Success criteria:**
- [ ] {Specific, verifiable criterion}
- [ ] {Specific, verifiable criterion}
**Demo capability:** {What can be demonstrated}
**Feedback questions:**
- {What we want to learn by this milestone}
Verification: At least 2-3 milestones defined with clear success criteria.
If you can't continue: Milestones unclear → Default to: Walking Skeleton (2 features) → MVP (60% features) → Complete (100%).
Step 6: Estimate Timeline (Optional)
Map features to time periods if deadline exists.
Timeline estimation approach:
- •Reference calibration data: Use
.claude/rai/calibration.mdfor velocity - •Apply velocity multiplier: Kata cycle = 2-3x faster than traditional estimates
- •Add buffer: 20-30% buffer for unknowns, integration, polish
- •Back-calculate from deadline: Work backward from external dates
Timeline mapping:
| Period | Features | Milestone | Cumulative |
|---|---|---|---|
| Day 1-2 | F{N}.1, F{N}.2 | M1: Walking Skeleton | 30% |
| Day 3-4 | F{N}.3, F{N}.4 | - | 60% |
| Day 5-6 | F{N}.5 | M2: Core MVP | 80% |
| Day 7-8 | F{N}.6, F{N}.7 | M3: Feature Complete | 100% |
| Day 9 | Integration, polish | M4: Epic Complete | Done |
Velocity assumptions (based on calibration):
| Feature Size | Without Kata | With Full Kata Cycle |
|---|---|---|
| XS | 1-2 hours | 20-40 min |
| S | 2-4 hours | 40-90 min |
| M | 4-8 hours | 1.5-3 hours |
| L | 8-16 hours | 3-6 hours |
Verification: Timeline fits constraints, or scope adjusted.
If you can't continue: No deadline → Skip detailed timeline; use milestones for progress.
Step 7: Plan Progress Tracking
Define how progress will be measured and communicated.
Tracking mechanisms:
- •Feature completion: Simple checklist (most reliable)
- •Milestone achievement: Binary checkpoints (good for stakeholders)
- •Burndown: Story points over time (useful for trending)
- •Time tracking: Actual vs estimated (calibration data)
Recommended approach (RaiSE):
## Progress Tracking
| Feature | Size | Status | Actual Time | Notes |
|---------|:----:|:------:|:-----------:|-------|
| F{N}.1 | S | ✓ | 45 min | - |
| F{N}.2 | M | ✓ | 2h | - |
| F{N}.3 | S | IN PROGRESS | - | Started Day 3 |
| F{N}.4 | S | Pending | - | - |
**Milestones:**
- [x] M1: Walking Skeleton (Day 2) ✓
- [ ] M2: Core MVP (Day 5)
- [ ] M3: Feature Complete (Day 7)
- [ ] M4: Epic Complete (Day 9)
**Velocity:** {X.Y}x average (updated per story)
Tracking cadence:
- •Update after each story completion
- •Milestone check at end of each day/session
- •Velocity recalculation after 3+ features
Verification: Tracking table added to epic scope document.
If you can't continue: Tracking seems overhead → Minimum = feature checklist + milestone dates.
Step 8: Document Sequencing Rationale
Capture why features are ordered this way for future reference.
For each story, note:
- •Position rationale (why this order?)
- •Dependencies (what does it need? what does it enable?)
- •Risk factors (what could go wrong?)
- •Parallel opportunity (can it run with others?)
Rationale template:
## Feature Sequencing Rationale
### F{N}.1: {Feature Name}
- **Position:** First
- **Rationale:** Foundation required by all other features
- **Dependencies:** None
- **Enables:** F{N}.2, F{N}.3, F{N}.4
- **Risk:** Low (well-understood pattern)
- **Parallel:** No (blocking)
### F{N}.2: {Feature Name}
- **Position:** Second (after F{N}.1)
- **Rationale:** Core capability, validates architecture
- **Dependencies:** F{N}.1
- **Enables:** F{N}.5
- **Risk:** Medium (new integration)
- **Parallel:** No (on critical path)
Verification: Sequencing rationale documented for each story.
If you can't continue: Rationale obvious → Brief notes sufficient; don't over-document.
Step 9: Identify Risks and Mitigations
Review risks with sequencing lens.
Sequencing-specific risks:
| Risk Type | Example | Mitigation |
|---|---|---|
| Blocker risk | Foundation feature harder than expected | Early start, timebox spike |
| Integration risk | Parallel streams conflict at merge | Plan integration points |
| Velocity risk | First features slower than expected | Build in buffer, adjust after |
| External risk | API not ready when needed | Sequence dependent features later |
Risk-based sequencing adjustments:
- •High-risk feature early → More time for recovery
- •External dependency mid-epic → Plan fallback path
- •Integration complexity → Reduce parallel streams
Verification: Top 3 sequencing risks identified with mitigations.
If you can't continue: Risks identified in
/rai-epic-design→ Reference those; add sequencing-specific risks.
Step 10: Update Epic Scope Document
Add planning outputs to the scope document.
Sections to add:
## Implementation Plan
### Feature Sequence
| Order | Feature | Size | Dependencies | Milestone | Notes |
|:-----:|---------|:----:|--------------|-----------|-------|
| 1 | F{N}.1 | S | None | M1 | Foundation |
| 2 | F{N}.2 | M | F{N}.1 | M1 | Core capability |
| 3 | F{N}.3 | S | F{N}.2 | M2 | Can parallel with F{N}.4 |
| 4 | F{N}.4 | S | F{N}.1 | M2 | Can parallel with F{N}.3 |
| 5 | F{N}.5 | S | F{N}.3, F{N}.4 | M3 | Integration |
### Milestones
| Milestone | Features | Target | Success Criteria |
|-----------|----------|--------|------------------|
| M1: Walking Skeleton | F{N}.1, F{N}.2 | Day 2 | E2E path works |
| M2: Core MVP | +F{N}.3, F{N}.4 | Day 5 | Demo-able value |
| M3: Feature Complete | +F{N}.5 | Day 7 | All features done |
| M4: Epic Complete | - | Day 9 | Done criteria met |
### Parallel Opportunities
- **Stream 1:** F{N}.1 → F{N}.2 → F{N}.5 (critical path)
- **Stream 2:** F{N}.3, F{N}.4 (after F{N}.1, parallel with Stream 1)
### Progress Tracking
| Feature | Size | Status | Actual Time | Notes |
|---------|:----:|:------:|:-----------:|-------|
| F{N}.1 | S | Pending | - | - |
| F{N}.2 | M | Pending | - | - |
| ... | ... | ... | ... | ... |
Verification: Epic scope document updated with planning sections.
If you can't continue: Scope doc not found → Create minimal planning section in appropriate location.
Step 11: Validate Plan
Self-review checklist before starting implementation.
Plan validation:
- • All features sequenced with rationale
- • Critical path identified
- • At least 2 milestones defined (Walking Skeleton + MVP minimum)
- • Dependencies verified (no cycles, blockers identified)
- • Parallel opportunities documented (or explained why sequential)
- • Progress tracking setup in scope document
- • Top risks have mitigation strategies
- • Timeline fits deadline (if applicable)
Validation questions:
- •Could someone else start implementation from this plan?
- •Is the first feature clear and unblocked?
- •Are milestones meaningful (not just arbitrary splits)?
- •Does the plan reflect what we learned in
/rai-epic-design?
Verification: All validation checkboxes checked.
If you can't continue: Validation fails → Address gaps before starting implementation.
Step 12: Emit Epic Complete (Telemetry)
Record the completion of the plan phase:
rai memory emit-work epic {epic_id} --event complete --phase plan
Example: rai memory emit-work epic E9 -e complete -p plan
Output
- •Primary:
work/epics/e{N}-{name}/scope.md— updated with implementation plan - •Sections added: Feature sequence, milestones, parallel opportunities, progress tracking
- •Next:
/rai-story-designfor first feature in sequence
Implementation Plan Template
Add to epic scope document:
---
## Implementation Plan
> Added by `/rai-epic-plan` - YYYY-MM-DD
### Feature Sequence
| Order | Feature | Size | Dependencies | Milestone | Rationale |
|:-----:|---------|:----:|--------------|-----------|-----------|
| 1 | F{N}.1 | {S} | None | M1 | {Why first?} |
| 2 | F{N}.2 | {M} | F{N}.1 | M1 | {Why second?} |
| 3 | F{N}.3 | {S} | F{N}.2 | M2 | {Why here?} |
| ... | ... | ... | ... | ... | ... |
### Milestones
| Milestone | Features | Target | Success Criteria | Demo |
|-----------|----------|--------|------------------|------|
| **M1: Walking Skeleton** | F{N}.1, F{N}.2 | {Date/Day} | {What proves it works?} | {What can be shown?} |
| **M2: Core MVP** | +F{N}.3, F{N}.4 | {Date/Day} | {What proves value?} | {What feedback to gather?} |
| **M3: Feature Complete** | +F{N}.5... | {Date/Day} | All planned features done | Full capability demo |
| **M4: Epic Complete** | - | {Date/Day} | Done criteria met | `/rai-epic-close` ready |
### Parallel Work Streams
Time → Stream 1 (Critical): F{N}.1 ─► F{N}.2 ─► F{N}.5 ↓ Stream 2 (Parallel): F{N}.3 ─► merge ↑ Stream 3 (Parallel): F{N}.4 ───┘
**Merge points:**
- After F{N}.1: Split into parallel streams
- Before F{N}.5: Merge parallel streams
### Progress Tracking
| Feature | Size | Status | Actual | Velocity | Notes |
|---------|:----:|:------:|:------:|:--------:|-------|
| F{N}.1 | S | Pending | - | - | |
| F{N}.2 | M | Pending | - | - | |
| F{N}.3 | S | Pending | - | - | |
| ... | ... | ... | ... | ... | |
**Milestone Progress:**
- [ ] M1: Walking Skeleton ({target date})
- [ ] M2: Core MVP ({target date})
- [ ] M3: Feature Complete ({target date})
- [ ] M4: Epic Complete ({target date})
### Sequencing Risks
| Risk | Likelihood | Impact | Mitigation |
|------|:----------:|:------:|------------|
| {Risk 1} | {H/M/L} | {H/M/L} | {Strategy} |
| {Risk 2} | {H/M/L} | {H/M/L} | {Strategy} |
### Velocity Assumptions
- **Baseline:** {X.Y}x multiplier with kata cycle (from calibration)
- **Adjustment:** {Any epic-specific factors}
- **Buffer:** {20-30%} for integration/polish
---
*Plan created: YYYY-MM-DD*
*Next: `/rai-story-design` for F{N}.1*
Quality Standards
| Metric | Target |
|---|---|
| Planning time | <1 hour for typical epic |
| Plan reviewable | <5 minutes to understand sequence |
| Milestones per epic | 2-4 (Walking Skeleton + MVP minimum) |
| Sequencing rationale | 1-2 sentences per story |
| Risk coverage | Top 3 sequencing risks addressed |
Common Pitfalls
- •Over-planning — Detailed hour-by-hour schedules that become obsolete immediately
- •Ignoring risk — Sequencing by size instead of uncertainty; save risky features for last
- •No walking skeleton — Jumping to complex features without proving architecture works
- •Milestone-free — No intermediate checkpoints; progress invisible until end
- •Ignoring parallel opportunities — Sequential when parallel is possible (especially with AI-assisted work)
- •Timeline without buffer — Every hour accounted for; no room for learning
- •Planning without calibration — Estimates based on intuition instead of measured velocity
- •Sunk cost sequencing — "We already started X, so finish it" instead of re-evaluating
Integration with Memory Model
This skill supports the three-layer memory model:
Identity Layer (always loaded): Core values guide sequencing decisions (risk-first, lean principles)
Memory Layer (MVC queryable):
- •Past epic patterns inform sequencing
- •Calibration data enables realistic estimates
- •Process learnings (what worked before)
Long-term Layer (on-demand):
- •Historical velocity trends
- •Similar epic comparisons
Update memory after planning:
- •Note sequencing decisions in session log
- •Capture velocity assumptions for calibration
- •Document novel sequencing patterns
References
- •Epic Design:
/rai-epic-design(produces input for this skill) - •Epic Scope Examples:
work/epics/e01-foundation/scope.md,work/epics/e02-governance/scope.md - •Feature Planning:
/rai-story-plan(similar concept at story level) - •Epic Close:
/rai-epic-close(retrospective after completion) - •Calibration Data:
.raise/rai/memory/calibration.jsonl(velocity patterns) - •Constitution:
framework/reference/constitution.md(Lean principles) - •Guardrails:
governance/guardrails.md(quality standards)
External References
- •Walking Skeleton - Product Manager's Guide
- •Epic Implementation Strategies - Scaled Agile
- •Milestones for Agile Project Management
- •Master Agile Projects with Epics and Milestones
Relationship to Other Skills
Project Level
↓
/rai-epic-design ← Scope, features, ADRs
↓
/rai-epic-plan ← YOU ARE HERE (sequence, milestones, tracking)
↓
/rai-story-design → /rai-story-plan → /rai-story-implement → /rai-story-review
↓
/rai-epic-close ← Retrospective, learnings
From /rai-epic-design: Receives feature list with sizes, dependencies, risks
To /rai-story-design: Provides sequenced list, identifies first feature to start