AgentSkillsCN

estimating-work

估算开发任务的工作量。当规划冲刺、路线图或项目时间表时使用。涵盖故事点、相对估算和不确定性。

SKILL.md
--- frontmatter
name: estimating-work
description: Estimate effort for development tasks. Use when planning sprints, roadmaps, or project timelines. Covers story points, relative estimation, and uncertainty.
allowed-tools: Read, Glob, Grep

Estimating Work

Estimation Approaches

Story Points

Relative complexity, not time.

PointsComplexity
1Trivial, well understood
2Simple, minor unknowns
3Moderate complexity
5Complex, some unknowns
8Very complex, significant unknowns
13Extremely complex, many unknowns
21+Too big, needs decomposition

T-Shirt Sizing

For high-level estimates.

SizeRelative Effort
XSHours
S1-2 days
M3-5 days
L1-2 weeks
XL2-4 weeks

Estimation Factors

Consider:

  • Complexity: How difficult is the problem?
  • Uncertainty: How much is unknown?
  • Effort: How much work is involved?
  • Risk: What could go wrong?

Estimation Techniques

Planning Poker

  1. Present the task
  2. Everyone selects estimate privately
  3. Reveal simultaneously
  4. Discuss outliers
  5. Re-estimate if needed

Three-Point Estimation

code
Expected = (Optimistic + 4×Likely + Pessimistic) / 6

Reference Stories

Keep calibration stories:

  • "This 3-point story took 2 days"
  • "This 8-point story took a week"

Common Pitfalls

  • Anchoring: First estimate biases others
  • Optimism: Underestimating unknowns
  • Scope Creep: Original estimate doesn't match final scope
  • Ignoring Overhead: Code review, testing, deployment

Tips

  1. Estimate in ranges, not points
  2. Include buffer for unknowns
  3. Track actual vs. estimated
  4. Re-estimate when scope changes
  5. Don't estimate in hours (use relative sizing)