Timeline Planning Skill
Generate Mermaid Gantt charts that visualize project timelines, task scheduling, phases, and milestones based on GitHub issues and their estimates.
When to Use
Activate this skill when:
- •User asks "what would the timeline look like?"
- •User says "create a Gantt chart", "show me the project schedule"
- •After issue decomposition to visualize scheduling
- •During sprint planning to allocate work
Available Tools
| Tool | Purpose |
|---|---|
list_github_issues | Get issues with estimates and dependencies |
add_note | Save timeline to project notes |
search_github_issues | Find specific issues for timeline |
Mermaid Gantt Syntax
Basic Structure
mermaid
gantt
title Project Timeline
dateFormat YYYY-MM-DD
section Phase 1
Task A :a, 2025-01-15, 2d
Task B :b, after a, 3d
section Phase 2
Task C :c, after b, 2d
Key Elements
- •
title- Chart title - •
dateFormat- How dates are parsed - •
section- Groups related tasks - •Task format:
Name :id, start, duration
Estimate to Duration Conversion
Convert T-shirt size estimates to days:
| Estimate | Duration | Notes |
|---|---|---|
| Small | 1d | Single-day task |
| Medium | 3d | Few days of work |
| Large | 5d | Almost a week |
| XL | 8d | Full week+ |
Adjust based on:
- •Team velocity
- •Complexity indicators
- •Buffer for unknowns
Task States
| Modifier | Meaning | Example |
|---|---|---|
done | Completed | Task A :done, a, 2025-01-15, 2d |
active | In progress | Task B :active, b, after a, 3d |
crit | Critical path | Task C :crit, c, after b, 5d |
milestone | Milestone | MVP :milestone, m, after c, 0d |
Timeline Patterns
Linear Project
mermaid
gantt
title API Development
dateFormat YYYY-MM-DD
section Setup
Project initialization :a, 2025-01-15, 1d
Database setup :b, after a, 2d
section Development
User endpoints :c, after b, 3d
Auth endpoints :d, after c, 3d
section Testing
Unit tests :e, after d, 2d
Integration tests :f, after e, 2d
Parallel Workstreams
mermaid
gantt
title Full Stack Development
dateFormat YYYY-MM-DD
section Backend
API Design :a, 2025-01-15, 2d
API Implementation :b, after a, 5d
section Frontend
UI Design :c, 2025-01-15, 3d
UI Implementation :d, after c, 5d
section Integration
Connect Frontend-Backend :e, after b d, 3d
End-to-end tests :f, after e, 2d
With Milestones
mermaid
gantt
title Release Timeline
dateFormat YYYY-MM-DD
section Phase 1
Core features :a, 2025-01-15, 10d
Alpha Release :milestone, m1, after a, 0d
section Phase 2
Additional features :b, after m1, 7d
Beta Release :milestone, m2, after b, 0d
section Phase 3
Polish and fixes :c, after m2, 5d
Production Release :milestone, m3, after c, 0d
With Critical Path
mermaid
gantt
title Project with Critical Path
dateFormat YYYY-MM-DD
section Critical Path
Database design :crit, a, 2025-01-15, 2d
Core API :crit, b, after a, 5d
Integration :crit, c, after b, 3d
section Parallel Work
Documentation :d, 2025-01-15, 10d
UI polish :e, after a, 5d
Timeline Generation Process
Step 1: Gather Issues
Use list_github_issues to get:
- •Issue titles
- •Estimates or labels indicating size
- •Dependencies or blocking relationships
Step 2: Determine Start Date
- •Use today's date as default start
- •Or ask user for preferred start date
- •Consider sprint boundaries
Step 3: Convert Estimates
Transform issue estimates to durations:
code
#101 [Small] → 1d #102 [Medium] → 3d #103 [Large] → 5d
Step 4: Respect Dependencies
Order tasks based on blocking:
code
#101 → start immediately #102 blocked by #101 → after #101 #103 blocked by #102 → after #102
Step 5: Group into Phases
Organize tasks into logical sections:
- •Setup/Foundation
- •Core Features
- •Testing
- •Polish
Step 6: Generate Gantt Chart
Create the Mermaid syntax with all tasks, dependencies, and phases.
Date Formats
| Format | Example |
|---|---|
YYYY-MM-DD | 2025-01-15 |
after id | after a |
Nd | 3d - duration in days |
Best Practices
- •Use sections - Group related tasks for clarity
- •Show dependencies - Use
after idto chain tasks - •Mark milestones - Highlight key deliverables
- •Indicate critical path - Use
:critfor must-do-first tasks - •Keep titles short - Fit in the chart view
- •Add buffer - Include slack for unknowns
Example Output
For a set of issues about user authentication:
mermaid
gantt
title User Authentication System
dateFormat YYYY-MM-DD
section Foundation
Setup auth module :a, 2025-01-20, 1d
Database schema :b, after a, 1d
section Core Auth
Registration endpoint :c, after b, 3d
Login endpoint :d, after b, 3d
Password reset :e, after c, 2d
section Security
JWT implementation :f, after d, 2d
Rate limiting :g, after f, 1d
section Testing
Unit tests :h, after e g, 2d
Integration tests :i, after h, 2d
section Milestone
Auth Complete :milestone, m1, after i, 0d
Handling Edge Cases
No Estimates
If issues lack estimates:
- •Use Medium (3d) as default
- •Flag for user to review
Circular Dependencies
If dependencies form a loop:
- •Error and ask user to resolve
- •Cannot generate valid timeline
Too Many Tasks
If > 20 tasks:
- •Group into summary tasks
- •Suggest breaking into phases
After Generating Timeline
- •Show total project duration
- •Identify the end date
- •Flag if timeline exceeds any stated deadlines
- •Offer to save to project notes
- •Suggest adding milestones if missing