Timeline Planning Skill

Generate Mermaid Gantt charts that visualize project timelines, task scheduling, phases, and milestones based on GitHub issues and their estimates.

When to Use

Activate this skill when:

  • User asks "what would the timeline look like?"
  • User says "create a Gantt chart", "show me the project schedule"
  • After issue decomposition to visualize scheduling
  • During sprint planning to allocate work

Available Tools

ToolPurpose
list_github_issuesGet issues with estimates and dependencies
add_noteSave timeline to project notes
search_github_issuesFind specific issues for timeline

Mermaid Gantt Syntax

Basic Structure

mermaid
gantt
    title Project Timeline
    dateFormat YYYY-MM-DD

    section Phase 1
    Task A :a, 2025-01-15, 2d
    Task B :b, after a, 3d

    section Phase 2
    Task C :c, after b, 2d

Key Elements

  • title - Chart title
  • dateFormat - How dates are parsed
  • section - Groups related tasks
  • Task format: Name :id, start, duration

Estimate to Duration Conversion

Convert T-shirt size estimates to days:

EstimateDurationNotes
Small1dSingle-day task
Medium3dFew days of work
Large5dAlmost a week
XL8dFull week+

Adjust based on:

  • Team velocity
  • Complexity indicators
  • Buffer for unknowns

Task States

ModifierMeaningExample
doneCompletedTask A :done, a, 2025-01-15, 2d
activeIn progressTask B :active, b, after a, 3d
critCritical pathTask C :crit, c, after b, 5d
milestoneMilestoneMVP :milestone, m, after c, 0d

Timeline Patterns

Linear Project

mermaid
gantt
    title API Development
    dateFormat YYYY-MM-DD

    section Setup
    Project initialization    :a, 2025-01-15, 1d
    Database setup           :b, after a, 2d

    section Development
    User endpoints           :c, after b, 3d
    Auth endpoints           :d, after c, 3d

    section Testing
    Unit tests               :e, after d, 2d
    Integration tests        :f, after e, 2d

Parallel Workstreams

mermaid
gantt
    title Full Stack Development
    dateFormat YYYY-MM-DD

    section Backend
    API Design              :a, 2025-01-15, 2d
    API Implementation      :b, after a, 5d

    section Frontend
    UI Design               :c, 2025-01-15, 3d
    UI Implementation       :d, after c, 5d

    section Integration
    Connect Frontend-Backend :e, after b d, 3d
    End-to-end tests        :f, after e, 2d

With Milestones

mermaid
gantt
    title Release Timeline
    dateFormat YYYY-MM-DD

    section Phase 1
    Core features           :a, 2025-01-15, 10d
    Alpha Release           :milestone, m1, after a, 0d

    section Phase 2
    Additional features     :b, after m1, 7d
    Beta Release            :milestone, m2, after b, 0d

    section Phase 3
    Polish and fixes        :c, after m2, 5d
    Production Release      :milestone, m3, after c, 0d

With Critical Path

mermaid
gantt
    title Project with Critical Path
    dateFormat YYYY-MM-DD

    section Critical Path
    Database design         :crit, a, 2025-01-15, 2d
    Core API                :crit, b, after a, 5d
    Integration             :crit, c, after b, 3d

    section Parallel Work
    Documentation           :d, 2025-01-15, 10d
    UI polish               :e, after a, 5d

Timeline Generation Process

Step 1: Gather Issues

Use list_github_issues to get:

  • Issue titles
  • Estimates or labels indicating size
  • Dependencies or blocking relationships

Step 2: Determine Start Date

  • Use today's date as default start
  • Or ask user for preferred start date
  • Consider sprint boundaries

Step 3: Convert Estimates

Transform issue estimates to durations:

code
#101 [Small] → 1d
#102 [Medium] → 3d
#103 [Large] → 5d

Step 4: Respect Dependencies

Order tasks based on blocking:

code
#101 → start immediately
#102 blocked by #101 → after #101
#103 blocked by #102 → after #102

Step 5: Group into Phases

Organize tasks into logical sections:

  • Setup/Foundation
  • Core Features
  • Testing
  • Polish

Step 6: Generate Gantt Chart

Create the Mermaid syntax with all tasks, dependencies, and phases.

Date Formats

FormatExample
YYYY-MM-DD2025-01-15
after idafter a
Nd3d - duration in days

Best Practices

  1. Use sections - Group related tasks for clarity
  2. Show dependencies - Use after id to chain tasks
  3. Mark milestones - Highlight key deliverables
  4. Indicate critical path - Use :crit for must-do-first tasks
  5. Keep titles short - Fit in the chart view
  6. Add buffer - Include slack for unknowns

Example Output

For a set of issues about user authentication:

mermaid
gantt
    title User Authentication System
    dateFormat YYYY-MM-DD

    section Foundation
    Setup auth module       :a, 2025-01-20, 1d
    Database schema         :b, after a, 1d

    section Core Auth
    Registration endpoint   :c, after b, 3d
    Login endpoint          :d, after b, 3d
    Password reset          :e, after c, 2d

    section Security
    JWT implementation      :f, after d, 2d
    Rate limiting           :g, after f, 1d

    section Testing
    Unit tests              :h, after e g, 2d
    Integration tests       :i, after h, 2d

    section Milestone
    Auth Complete           :milestone, m1, after i, 0d

Handling Edge Cases

No Estimates

If issues lack estimates:

  • Use Medium (3d) as default
  • Flag for user to review

Circular Dependencies

If dependencies form a loop:

  • Error and ask user to resolve
  • Cannot generate valid timeline

Too Many Tasks

If > 20 tasks:

  • Group into summary tasks
  • Suggest breaking into phases

After Generating Timeline

  • Show total project duration
  • Identify the end date
  • Flag if timeline exceeds any stated deadlines
  • Offer to save to project notes
  • Suggest adding milestones if missing