Plan Craft

Scope Sizing

Right-sizing scope is the first thing that separates useful plans from shelf-ware.

Too broad: never finishes, scope creep is built in, tasks are really epics in disguise. Too narrow: misses the point, creates follow-up plans that should have been one plan.

Signs Scope Is Wrong

  • "And" in the overview: "Rebuild the auth system AND add user profiles AND migrate the database" is three plans
  • Tasks that are really epics: if a task needs its own sub-tasks, the scope is too broad
  • Out-of-scope list longer than in-scope: you are defining the plan by what it is NOT
  • No out-of-scope list at all: scope creep waiting to happen
  • Cannot explain it in one sentence: if the overview needs a paragraph, the scope is too broad

The One-Sentence Test

Write one sentence that describes what this plan accomplishes. Not what it touches, not what it changes -- what it accomplishes for the user. If you need a comma followed by "and", it is too broad.

Good: "Allow users to reset forgotten passwords via a secure email link." Bad: "Improve the authentication system, add password reset, and update the user profile page."

Task Decomposition Quality

What Makes a Good Task

  • Small: completable in one focused session (30-90 minutes of implementation)
  • Independent: can be started without waiting on other tasks where possible
  • Verifiable: has a clear "done" signal that someone else can check
  • Ordered: logical sequence that builds on previous work
  • Specific: names the files affected and the changes needed

What Makes a Bad Task

  • Too big: "Implement the feature" -- that is the entire plan, not a task
  • Too vague: "Update stuff" or "Refactor as needed" -- no acceptance criteria possible
  • No done signal: how does the implementer know when to stop?
  • Hidden dependencies: task 5 quietly requires tasks 1-4 to be done in a specific way
  • Bundled concerns: "Add the endpoint and write the UI" -- that is two tasks

The Dependency Chain Test

If task N depends on tasks 1 through N-1, the tasks are not independent -- they are steps in a procedure. This is a sign the decomposition is wrong. Good decomposition has a task graph, not a task chain. Some parallelism should be possible.

Exception: genuinely sequential work (database migration before service code before API endpoint). Even then, tasks 3 and 4 often can be parallel.

Right Sizing

A task should be completable in one focused session. Guidelines:

SizeDescriptionExample
SSingle file, straightforward changeAdd a database migration
M2-3 files, some coordinationBuild a service with tests
LMultiple files, significant logicFull API endpoint with validation

If a task is larger than L, break it down further. If everything is S, you may be over-decomposing.

Common Planning Mistakes

The Big Ones

  1. Planning without exploring the codebase first: the number one mistake. You cannot plan changes to code you have not read. Every plan must start with exploration.

  2. Confusing approach with implementation: deciding HOW (specific libraries, patterns) before deciding WHAT (behavior, contracts, interfaces). Approach selection comes after scope definition.

  3. Missing the out-of-scope section: scope creep starts the moment someone says "while we're in there, we should also..." An explicit out-of-scope section is the defense.

Acceptance Criteria Failures

  • Not testable: "Make it better" or "Improve performance" -- better than what? By how much?
  • Not specific: "Handle errors properly" -- which errors? What is proper handling?
  • Not verifiable: no one can tell whether "clean up the code" was achieved
  • Missing the negative case: only describing what should happen, not what should NOT happen

Every acceptance criterion should complete the sentence: "I can verify this by..."

Sizing Mistakes

  • Over-planning: 20 tasks for a 3-file change. If the plan is longer than the implementation, something is wrong.
  • Under-planning: 1 task for a system redesign. If the task description needs sub-bullets with sub-bullets, it needs decomposition.

Assumption Traps

  • Assuming dependencies instead of verifying them: "This probably uses library X" is not a plan input -- read the code
  • Not presenting alternatives: making a unilateral decision about the approach denies the user meaningful choice
  • Unstated constraints: performance requirements, compatibility needs, and deployment constraints discovered during implementation, not planning

Plan Quality Signals

Good Signals

  • Every task has acceptance criteria AND verification steps
  • Risks section includes mitigations, not just a list of risks
  • Open questions are tracked and resolved before approval
  • Files affected are listed per task
  • Out-of-scope section exists and is specific
  • Alternatives were considered for the approach, with rationale for the selection
  • Effort estimates are present (S/M/L at minimum)

Bad Signals

  • Tasks without clear "done" criteria
  • No alternatives considered for the approach
  • Risks section is empty (everything has risks; an empty section means they were not considered)
  • Uncertainty flags left unresolved at approval time
  • No verification strategy (how do you know it works?)
  • Scope defined only by what is in, not what is out
  • Every task depends on the previous task (chain, not graph)

The Good Plan Test

Before approving any plan, run this checklist:

  1. Handoff test: can someone who was not in the planning conversation implement this without ambiguity?
  2. Session test: is every task completable in one focused session?
  3. Verification test: does every acceptance criterion have a verification method?
  4. Assumption test: are all assumptions stated explicitly?
  5. Boundary test: is the scope bounded with clear in AND out?
  6. Alternatives test: were alternatives considered and evaluated?
  7. Risk test: are risks identified with specific mitigations?
  8. Exploration test: was the codebase explored before tasks were defined?

A plan that fails any of these is not ready for implementation. Send it back for revision -- building from a bad plan wastes more time than fixing the plan.